The builder stubbed a toilet in the corner; you want it against the far wall with a shower where the stub is. That is drain relocation, and it is one of the most common jobs we do. It is more than moving a visible pipe: the new run has to hold slope back to the main or the ejector basin, the vent has to be re-established, the supply lines have to follow, and the slab comes up along the whole route. We scope all of it — cut, trench, pipe, vent, inspection, backfill, patch — as one fixed price.
When is this different from completing rough-ins?
If the fixtures are going where the stubs are, that is rough-in completion. If any fixture moves more than a few inches, the drain moves, and it is this page. Moving a toilet is the big one — a 3-inch line at ¼-inch-per-foot slope — and it decides whether gravity still works or the new location needs a pump. A sink or shower moving along the same wall is usually a smaller cut.
What we assess at the design visit
- Where the existing stubs connect and whether that connection is sound (camera where warranted).
- The invert elevation of the main and the slope available to the new toilet location.
- Where the vent can be picked up — the existing stack, a new vent through the wall above, or an AAV where the code for your city allows one (most metro jurisdictions limit AAVs; we check).
- What is under and over the slab along the route: footings, post pads, radon or sump pits, in-floor heat, finished flooring.
- Supply line routing to the new positions.
What the proposal names
New fixture positions on a plan; the abandoned stubs and how they are capped; the drain and vent route; whether an ejector becomes necessary; the slab area cut and patched; the inspections; what finished surfaces we restore (concrete patch, flush and level) and what we don't (tile, flooring). The proposal comparison guide shows the layout we use.
Does moving the toilet mean a pump?
Sometimes. Every foot you move a toilet away from where the main leaves the house costs a quarter-inch of fall. Move it far enough and the drain ends up below the main — at that point it needs an ejector basin. We tell you where that line is at the design visit, before you fall in love with a layout.
What it costs
A short relocation along one wall is a small slab cut and usually lands in the low thousands; moving a toilet across the room with a new vent is more, and crossing into ejector territory adds the basin and pump ($850–$3,500 installed nationally). Nationally a full bathroom rough-in runs $3,000–$20,000; a relocation of existing rough-ins usually prices inside the lower half of that. Fixed written price after the design visit.
Who does the work. Installed by our licensed Kansas City plumbing partner — 4.9 stars across 100+ Google reviews, BBB A+ rated, serving the metro since 2014. Those are the partner's credentials; the license, insurance and warranty for your job are written into your quote.
Get a quote
Send us a sketch or a photo of the stubs with your wanted layout marked on it, your city or ZIP, and whether the basement is finished. Get a quote → — or read the complete basement bathroom plumbing guide first.